2018
October
Complete Montrose-Nucla segment construction
2017
September
Begin Montrose-Nucla segment construction
August
Complete Montrose-Nucla right-of-way improvements
May 31
End Phase II construction of the 345kV Montrose Substation
April
Start Montrose-Nucla right-of-way improvements
March 21
Begin Phase II construction of the 345kV Montrose Substation
March 20
BLM and USFS issues Decision Documents
February
BLM FONSI received; 30 day appeal period ended March 23, 2017
February
Forest Service Finding Of No Significant Impact (FONSI) and Decision Notice received and considered final
January
Dolores and San Miguel County land use approvals
2016
December
End County Permitting (Montrose, Dolores and San Miguel Counties)
End BLM and USFS issues Decision Documents
November
Begin BLM and USFS Issues Decision Documents
October
End Phase I construction of the 345kV Montrose Substation
August
Final EA Released
June
Begin Phase I construction of the 345kV Montrose Substation
May
Begin County Permitting (Montrose, Dolores and San Miguel Counties)
2015
December
BLM begins analysis of public comments
Public comment period closed
November
BLM Public Workshop
5 to 7 p.m.
Dove Creek High School, 525 N. Main St. Dove Creek, CO 81324
Draft EA published by BLM
Public comment period began
2013
July
CPUC approved MNC Upgrade Transmission Project