Timeline

Timeline

2018

October

Complete Montrose-Nucla segment construction
 

2017

September

Begin Montrose-Nucla segment construction
 

August

Complete Montrose-Nucla right-of-way improvements
 

May 31

End Phase II construction of the 345kV Montrose Substation
 

April

Start Montrose-Nucla right-of-way improvements
 

March 21

Begin Phase II construction of the 345kV Montrose Substation

 

March 20

BLM and USFS issues Decision Documents
 

February

BLM FONSI received; 30 day appeal period ended March 23, 2017
 

February

Forest Service Finding Of No Significant Impact (FONSI) and Decision Notice received and considered final
 

January

Dolores and San Miguel County land use approvals
 

2016

December

End County Permitting (Montrose, Dolores and San Miguel Counties)
End BLM and USFS issues Decision Documents
 

November

Begin BLM and USFS Issues Decision Documents
 

October

End Phase I construction of the 345kV Montrose Substation
 

August

Final EA Released
 

June

Begin Phase I construction of the 345kV Montrose Substation
 

May

Begin County Permitting (Montrose, Dolores and San Miguel Counties)

 

2015

December

BLM begins analysis of public comments
Public comment period closed
 

November 

BLM Public Workshop
5 to 7 p.m.
Dove Creek High School, 525 N. Main St. Dove Creek, CO 81324
 

Draft EA published by BLM
Public comment period began
 

2013

July

CPUC approved MNC Upgrade Transmission Project